02OWG26 · OLYMPIC WINTER GAMES MILANO CORTINA 2026SAN SIRO · MILAN

FROM ACTIVE STADIUM
TO OLYMPIC STAGE.

Deputy Site Manager for GL events Live across a roughly six-month transformation programme: from the first build in Parco dei Capitani through an active football stadium, 17 days of exclusive use for the final Olympic phase, the Opening Ceremony, reset and final reinstatement.

Aerial view of San Siro during Milano Cortina 2026
ROLEDeputy Site Manager
TOTAL PROJECT CYCLE~6 months · build to reinstatement
EXCLUSIVE USE17 days · final Olympic phase
PEAK ENVIRONMENT~3,000 workforce & cast · 100+ companies

The San Siro project unfolded across roughly six months, beginning with the transformation of Parco dei Capitani and continuing through final reinstatement. The stadium itself could not simply be handed over months in advance: it remained a living football venue. Olympic work therefore developed through phased access, soft fit-out and parallel preparation until the final match opened a 17-day period of exclusive use.

The venue operation had to connect construction, temporary infrastructure, contractors, security, logistics, ceremonies, broadcast, hospitality and stadium interfaces — while respecting the reality that the building had another life before and immediately after the Games.

“By the final phase, we had become a machine. The venue looked different from morning to evening.”
700+programme activities / milestones
24/7accelerated final operating phase
~€9MGL scope managed / coordinated
31 MARParco dei Capitani restored on schedule
01

Parco dei Capitani / Build

An empty grass area became a rehearsal village: roads, temporary structures, commodities, toilets, utilities and services. Work moved through rain, cold, ice and mud until cast rehearsals could begin in December.

02

San Siro / Accelerate

Soft fit-out ran while football continued. The 17-day exclusive-use window began after the late-January match and the operation shifted to 24/7. Trucks, contractors, rehearsals, BOH/FOH/FOP changes and venue readiness compressed into days.

03

Ceremony / Reset

The Opening Ceremony took place on 6 February. Reverse operations started immediately: dismantling, restoration and the race to return the stadium to football use in ex-ante condition.

04

Parco dei Capitani / Restore

The rehearsal village disappeared. Temporary infrastructure was removed; the park was levelled, reseeded and handed back on 31 March as scheduled.

The visible moment was the ceremony. The operational project was larger: make space available at the right time, transform it safely, support the live event, then remove the event without leaving the venue trapped inside it.

PHASED HANDOVERTEMPORARY INFRASTRUCTURECONTRACTOR COORDINATIONVENUE READINESSLIVE DELIVERYRESET & REINSTATEMENT
PREVIOUS STORY · 01

AGJ26

Two venues, one operating system →
NEXT STORY · 03

OLYMPIC VILLAGE MILANO

Close-out, dismantling and handover →